A library, a fire station, a recreation centre. Follow what each project provides, how its budget changed, and which costs are still missing from the public record.
Source checks through Nov 27, 2026. A borrowing amount is not the whole cost of a project.
The planned building grew from 75,000 to 85,000 sq ft, then was reduced to 73,000 sq ft. The earlier comparison is expressed in September 2021 dollars including escalation; these are not identical scopes priced at the same date.
Read the library’s budget decisions and source documents
$62.70 million in 2021, up from $50.65 million in 2018, for the library and multi-use facility.
The figures are in September 2021 dollars including escalation, and part of the increase is the larger scope Council approved (75,000 to 85,000 sq ft).
Read the evidence & sources
Library/multi-use facility: on May 17, 2021 Council endorsed a larger scope - library 60,000 sq ft, multi-use space up to 25,000 sq ft, overall facility up to 85,000 sq ft (motion 2021-C-086, recorded vote 5-2, Mayor Brown and Councillor Jones against). On Oct 4, 2021 Council approved a project budget of $62,703,550 (motion 2021-C-347, recorded vote 6-1, Mayor Peter Brown the only vote against), up from the 'current approved project budget, set in 2018' of $50,650,185 ($6,447,185 pre-planning + $44,203,000 construction, for a 50,000 sq ft library + 25,000 sq ft multi-use = 75,000 sq ft); a May 17, 2021 estimate had been $62,002,000
$83.3 million Class C estimate against a $62.7 million library budget; Council then set a $65 million ceiling.
Read the evidence & sources
Library/multi-use facility: Nov 7, 2022 Class C estimate projected $83,315,550 vs the $62,703,550 budget (+$20,612,000; +/-20% accuracy). Administration recommended holding the budget at $62,703,550 (73,000 sq ft, parkade cut ~60 stalls). Council instead set the budget at $65,000,000 'for top end cost' (2022-C-447, Petrow, recorded 6-1, Mayor Brown opposed) and directed the Steering Committee to 'maintain the 125 stalls in the underground parkade' (2022-C-448, Petrow, recorded 5-2, Mayor Brown and Deputy Mayor Spearman opposed). On Dec 19, 2022 Council endorsed the re-alignment: 73,000 sq ft (53,000 library; 20,000 atrium + multi-use), 12,000 sq ft smaller than 85,000 (6,800 sq ft post-secondary space removed), redesign within $65,000,000, full-footprint parkade (+/- 115 stalls) (2022-C-542, Petrow, 'Carried', no recorded vote; Belyk and Kolson absent)
$60,496,085 forecast to finish the library, against the $65,000,000 budget.
This is a forecast at completion, measured against a budget Council had raised from $50,650,185 (2018) to $62,703,550 (2021) and then $65,000,000 (2022), while the building was cut from 85,000 to 73,000 sq ft (see the two items above).
Read the evidence & sources
Inspire (multi-use facility & library) final status report: baseline budget $65,000,000; committed $59,316,322; approved change orders $2,673,642; forecast cost at completion $60,496,085; forecast variance $4,503,914 under budget
A new fire station and the positions needed to staff it. Building costs and ongoing staffing costs are separate expenses.
What is still missing
A published total project budget. Identifiable funding is not a complete final cost, and the earlier plan is a different comparison point.
25 positions to staff the new fire station, with a $3.29 million reserve draw to phase in the cost.
Read the evidence & sources
Highland Park Fire Station staffing phase-in (2026 budget): the 2026 Council Approved Budget adds 25.0 full-time equivalent positions 'Fire positions to staff the new Highland Park Fire Station' at $4,114,000, offset by a $(3,291,000) 'Draw from Tax Stabilization Reserve to phase in the cost of new Fire positions'; City states 'Council approved the use of the Tax Stabilization Reserve to phase in these costs over five years' and 'the tax impact in 2026 was reduced to 0.9% from the originally projected 4.6%'. Council records: no separate motion on the phase-in was found; it was discussed in deliberations (Nov 28, 2025: Finance 'clarified regarding the draw from the Tax Stabilization Reserve to phase in the cost of the Fire positions over four years'; Dec 9, 2025: 'It was asked what the impact would be to draw ... over five years rather than four years') and approved only as part of the 2026 budget adoption: 2025-C-381 (2026 Operating Budget $299,164,206) moved by Councillor Glass; 2025-C-383 (4.6% municipal tax adjustment) moved by Councillor Kolson; carried, no recorded vote
Follow the fire station’s funding and approval record
2024 is when Council approved the Highland Park Fire Station project, according to the 2026 budget book.
This rests on the City’s later statement; the 2024 approving motion itself is not saved in the dataset.
Read the evidence & sources
The 2026 book, p.13: “In 2024, Council approved the capital project for the new Highland Park Fire Station.” That falls in the previous council’s term (elected October 2021).
$29.46 million borrowing bylaw for the Highland Park Fire Station, passed April 2, 2024.
Read the evidence & sources
Highland Park Fire Station: Borrowing Bylaw B-07/2024 (long-term borrowing of $29,460,200 for the portion of the project to be funded by long-term borrowing) received second reading (2024-C-135, Belyk) and third reading (2024-C-136, Jones) on Apr 2, 2024, both Carried; per the agenda report, outstanding debt would rise to $96,073,892 (cumulative $111,269,992 with the three bylaws that day)
$8,925,170 added to the Highland Park Fire Station budget after a closed session.
Read the evidence & sources
Mar 18, 2025: Council approved (motion 2025-C-097, moved by Coun. Al Jones, 'Carried', no recorded vote; Belyk absent) an $8,925,170 capital budget amendment for the Highland Park Fire Station (Project #000505) funded from the General Capital Reserve, after a closed session with JLL Project Management. DiscoverAirdrie: no councillors voiced opposition; Mayor Brown: 'prices are going through the roof'. Apr 15, 2025 City update: Class D estimate omitted contingency, SCBA/air stations, soft costs (permits, design fees), power line work, hydrants/fibre, traffic controls, IT and accessibility items; construction inflation 4.7% (2023), 3.4% (2024), 2.8% expected (2025)
40.7% above the 2022 plan, at least, in identifiable approved funding for the Highland Park Fire Station. The City has not published a total.
This is a floor, not a total: the City has not published a total project budget. The base is a 10-year plan figure in 2022 dollars, not an approved total.
Conflicting figure: Alberta Major Projects lists the project at $29.0M.
Read the evidence & sources
Highland Park Fire Station (project 000505) - estimate vs latest: Dec 2022 Final Recommended 2023-2032 Capital Plan (a 10-year plan figure, not a project budget) listed 'Fourth Fire Hall - Design & Construction' at $155,100 (2023), $2,300,500 (2024) and $24,834,200 (2025) = $27,289,800 (our calculation); DiscoverAirdrie (Nov 24, 2022) reported 'a total estimated cost of $27 million'. 2024 budget: portion 'to be funded by long-term borrowing is $29,460,200' (Borrowing Bylaw B-07/2024). Mar 18, 2025: Council added an $8,925,170 capital budget amendment from the General Capital Reserve . The City has not published a total project budget ('Council has been previously given a detailed budget in a closed session'). City reasons for the increase: construction inflation 4.7% (2023), 3.4% (2024), 2.8% expected (2025), and items 'not included within the original consultant reports at a class D level' (contingency, SCBA/air stations, soft costs, power line work, hydrants/fibre, traffic controls, IT, accessible components). City says 'no new space has been approved' and about 300 square metres of building was removed. Apr 14, 2026: Fire Chief Pirie said 'it's on time. It's on budget' and expected savings 'I would use the word millions' (news). Conflict: Alberta Major Projects lists 'Estimated Cost: $29.0M', below the identifiable City funding - unresolved.
A recreation centre project. Borrowing decisions show part of its funding; they do not establish its complete cost or its value to residents.
What is still missing
The total project budget has not been published in the checked record. Grants and developer charges also contribute to funding.
Read the proposed borrowing and the project’s funding history
our calculation
$146,528,436 in Borrowing Bylaw B-39/2026 for the Southwest Recreation Centre had first reading only on Nov 17, 2026, carried with no recorded vote. If the bylaw passes, borrowing would be $249,148,247, 99.7% of the $250 million set aside in 2023: our calculation, and only if the bylaw passes.
Read the evidence & sources
Draft minutes of the Nov 17, 2026 regular Council meeting (eScribe DocumentId=22012, included at p.12 of the Dec 1, 2026 agenda package and scheduled for confirmation at that meeting) record First Reading of Borrowing Bylaw B-39/2026: 2026-C-329 Moved By Deputy Mayor Glass, 'That Council gives First Reading to Borrowing Bylaw B-39/2026, being a bylaw to fund $146,528,436 of the Southwest Recreation Centre project.' Carried (no recorded vote; the minutes do not say 'Carried Unanimously'). All seven members were listed present at the start of the meeting (Mayor H. Spearman; Councillors R. Chapman, C. Kolson; Deputy Mayor C. Glass; Councillors K. Shima, S. Obasan, C. Stewart). Second and third readings follow the advertising and petition period. Previously approved by the 2021-2025 (Brown) council: B-05/2024 $12,629,800 (SWRC Design) and B-01/2025 $89,990,011 (SWRC Phase 1; first reading Dec 3, 2024, 2024-C-387 moved by Councillor Jones (Kolson absent); second reading Jan 21, 2025, 2025-C-011 moved by Councillor Petrow; third reading 2025-C-012 moved by Councillor Chapman; each carried, no recorded vote), together $102,619,811 (~$102.6M, our calculation). The $146,528,436 first reading is before the 2025-2029 (Spearman) council; the Nov 17, 2026 agenda report says with B-39/2026 'the total borrowing required to fund Project 271 is $249,148,247' - total SWRC borrowing would reach $249.1M only if B-39/2026 passes second and third readings. City declined to release total project budget citing procurement
Borrowing Bylaw B-39/2026, for $146,528,436, had first reading only on Nov 17, 2026, moved by Deputy Mayor Glass and carried with no recorded vote. If the bylaw passes, borrowing for the Southwest Recreation Centre would be $249,148,247, 99.7% of the $250 million set aside in 2023: our calculation, and only if the bylaw passes.
Read the evidence & sources
Borrowing Bylaw B-39/2026 would fund $146,528,436 of the Southwest Recreation Centre project. Council gave it first reading on Nov 17, 2026. The motion carried, with no recorded vote. No second or third reading is in those minutes. If the bylaw passes, borrowing for the project would be $249,148,247. That is 99.7% of the $250 million set aside in 2023, our calculation, and only if the bylaw passes. The figure is not in force.
On July 7, 2026, Council carried a debt-funded amendment for the Southwest Recreation Centre, with the amount kept in a closed meeting. A later summary lists $147,612,779 on its own, and the City has not said the two are the same.
Read the evidence & sources
July 7, 2026 agenda report: Administration recommended concurrent delivery of the full SWRC and 'a budget amendment funded from debt, as outlined within in-camera budget amendment report'; Phase 1 cost increases require a budget amendment regardless of option; cumulative tax impacts approx. 10% over five-to-six years, annual impacts kept at or below ~2% using Tax Stabilization Reserve. On Jul 7, 2026 Council approved a debt-funded amendment for Project 000271 (amount in camera). Separately, the Q3 2026 summary lists a $147,612,779 amendment for 000271. The City hasn't said these are the same amendment.
Existing borrowing bylaws allow up to 20 years, at a rate not above 10%. Borrowing Bylaw B-39/2026, which has had first reading only, would allow 25 years at the same cap.
Read the evidence & sources
Borrowing bylaw terms: B-05/2024 SWRC Design $12,629,800, B-07/2024 Highland Park Fire Station $29,460,200 (both read Mar 4 and Apr 2, 2024) and B-01/2025 SWRC Phase 1 $89,990,011 each allow borrowing 'for a period not to exceed twenty (20) years from the Government of Alberta - Loans to Local Authorities, or another authorized financial institution', repaid 'at a rate not exceeding the interest rate fixed by the Government of Alberta - Loans to Local Authorities or another authorized financial institution on the date of the borrowing and not to exceed ten (10) percent'. Proposed B-39/2026 ($146,528,436, first reading Nov 17, 2026) uses the same 10 percent cap but 'a period not to exceed twenty-five (25) years'
Infrastructure also includes the less visible systems residents use every day. These records track budget changes, rather than assuming that an amendment is a final project cost.
Water infrastructure and the wider project program
$69,510,376 added to the capital budget on November 3, 2026, for the forcemain to Calgary.
Read the evidence & sources
Nov 3 2026: Council approved 'a capital budget amendment in the amount of $69,510,376 for Project #1206 [editor's insertion - project name per 2026 Council Approved Budget PDF p.122: 'Wastewater Forcemain Construction to Calgary'], with $48,553,890 being funded by the City of Calgary and $20,956,486 being funded by future developer levies'
The City’s own reports say some projects were under-estimated, and the revised amounts are not published.
Read the evidence & sources
Other capital projects the City itself flags as under-estimated (amounts not published): (1) Sagewood Canal Stormwater Management Improvements (001275) - Dec 2022 plan $103,400 + $1,055,000 = $1,158,400 (our calculation); Dec 2025 report: 'The Opinion of Probable Costs (OPC) underestimated costs and therefore the 2025 budget request was insufficient'; amendment approved in the 2026 budget; 2026 book: 'the scope and cost of the project have increased beyond previously approved funding levels' (two larger-diameter pipes needed). (2) Nose Creek Bridge - 8 Street north of Veterans Blvd (000987): 'Due to elevated construction costs, the initial budget was insufficient and the schedule for replacement was extended to 2026.' (3) Public Works Yard Redevelopment (000915): two design projects 'Currently on hold ... due to underestimated Opinion of Probable Costs (OPC)'.
$303,812,229 in the 2025 major capital program, including $17,241,345 in that year’s budget amendments.
Read the evidence & sources
2025 major capital projects: 42 projects totalling $303,812,229, 'which includes $138,319,011 in new approved projects, $148,251,873 of carry forward projects from prior years and $17,241,345 in 2025 budget amendments' (Dec 2025 report; the May 2025 report had 42 projects totalling $295,621,229). The City's quarterly capital variance summaries state: 'Budget, projections and variance information were removed for projects underway where pricing is not secured. These amounts were removed in order to protect the City of Airdrie's procurement process.'
Capital spending buys or builds long-lasting assets. The chart shows actual yearly spending, including utility infrastructure; large projects can make one year look very different from the next.
Capital spending each year
What the City reported to the Province as money spent on capital assets, including utility capital. Not adjusted for inflation.